2010 is going to be a busy year. The Lake County Division of Transportation has a wide range of projects scheduled for this Spring; from several road resurfacings to 3 new roundabouts as well as the widening of Washington St. All of the 2010 projects are posted on our Constuction Projects interactive webmap.
Washington St. from IL 21 to US Route 41: Project is nearing completion. All lanes are open. Median landscaping in Spring 2010.
Washington St. from Hunt Club Rd. to IL 21: Crews have begun excavation on the North side of Washington St. and installing temporary pavement.
North Ave. from IL 83 to Deep Lake Rd: New storm sewer has been installed. Utility companies will continue moving their facilities until Spring 2010.
Midlothian Rd. Extension: The final segment of the Midlothian Rd. extension is scheduled to begin Spring 2010.
MLK Jr. Dr. from Green Bay Rd. to Sheridan Rd: The north half of the roadway is nearing completion. Reconstruction of the south half will start in the Spring of 2010.
Riverwoods Rd. at Everett Rd. Construction of a roundabout is scheduled to begin in Spring 2010.
Hunt Club Rd. at Wadsworth Rd. Construction of a roundabout is scheduled to begin in Spring 2010.
Hunt Club Rd. at Millburn Rd. Construction of a roundabout is scheduled to begin in Spring 2010.